Ordsall Surgery



Dortech Maintenance Case Study

Ordsall Surgery

Reducing overheating and avoiding air conditioning through solar-control reglazing.

Ordsall Surgery

ClientOrdsall Surgery
Building typeHealthcare / GP surgery
Issue reportedOverheating in patient waiting areas and consulting rooms
Primary orientation affectedSouth and south-west facing glazing
Glazing areaApproximately 92m²
Existing building conditionNot air conditioned

Improved comfort

Reduced solar heat transmission supports more comfortable patient and staff spaces.

Avoided mechanical cooling

The glazing upgrade avoided a much larger air-conditioning capital cost.

Reduced running-cost exposure

The project improved passive performance without introducing new cooling running costs.

Case study overview

Dortech Maintenance helped Ordsall Surgery improve patient and staff comfort, enhance the appearance of the building and avoid costly mechanical cooling through targeted glazing replacement.

The challenge: summer overheating

Ordsall Surgery was experiencing significant overheating within its patient waiting area and consulting rooms during summer months. The affected areas were predominantly south and south-west facing, meaning they were exposed to high levels of direct and late-afternoon solar gain.

The client had been considering air conditioning. Before committing to mechanical cooling, Dortech reviewed the existing glazing and considered whether the overheating problem could be addressed through the building fabric itself.

Site assessment and retained frames

Following a site visit, Dortech established that the existing window and facade frames were in good condition. This created an opportunity to retain the existing frames and replace only the insulated glass units.

This approach reduced unnecessary material replacement, limited disruption to the surgery, and created a more cost-effective route to improving solar-control performance.

Glass performance improvement

Performance measure Existing glazing Replacement glazing Improvement
Light transmission 0.79 / 79% 0.47 / 47% Reduced excessive solar brightness
g-value / solar factor 0.63 / 63% 0.21 / 21% Major solar heat reduction
Approx. centre-pane Ug-value Assumed older DGU Approx. 1.0 W/m²K Improved winter insulation

Dortech recommended Saint-Gobain COOL-LITE XTREME 50/22 II high-performance solar-control glass. The replacement glass reduced visible light transmission from 79% to 47% and reduced the g-value from 63% to 21%, representing approximately 67% less solar energy transmission.

Reducing the cause, not treating the symptom

Instead of allowing solar heat to enter the building and then using air conditioning to remove it, the upgraded glazing reduced unwanted solar gain at source.

The project covered approximately 92m² of glazing, and the client confirmed that the cost of replacing the glass was less than half the cost of the air-conditioning option being considered.

Indicative energy and avoided cooling benefit

Benefit Indicative result
Useful heat reduction Approximately 7,507 kWh per year
Avoided gas input Approximately 8,832 kWh per year
Indicative heating-side saving Approximately £456 per year
Theoretical solar heat reduction Approximately 21,329 kWh per year
Avoided cooling electricity demand if AC had been installed Approximately 1,777 to 4,799 kWh per year
Avoided cooling energy cost Approximately £394 to £1,065 per year
Because the building was not previously air conditioned, there was no existing cooling electricity bill to reduce. The larger benefit was avoiding a much larger capital investment in air conditioning and preventing new running costs.

Result

By replacing the glass rather than installing air conditioning, Dortech Maintenance helped the client reduce solar heat transmission by approximately 67%, improve comfort for patients and staff, avoid significant capital expenditure, and introduce no additional cooling running costs.

The project also improved the thermal performance of the building envelope, supporting better year-round building performance.

Calculation assumptions

Assumption Value
Glazing area 92m²
Existing glass light transmission 0.79 / 79%
Replacement glass light transmission 0.47 / 47%
Existing glass g-value 0.63 / 63%
Replacement glass g-value 0.21 / 21%
G-value reduction 0.42
Assumed existing Ug-value 2.7 W/m²K
Assumed replacement Ug-value 1.0 W/m²K
Heating degree days 2,000 K-days/year
Assumed heating efficiency 85%
Assumed gas rate 5.16p/kWh
Assumed electricity rate 22.19p/kWh

Disclaimer: This case study is provided for general guidance. Performance data and energy savings are indicative only and actual results will vary depending on building design, occupancy, HVAC systems, operating conditions, weather, maintenance and energy costs.