Main Contractors, BAM Construction contacted Dortechs Maintenance team in respect to issues with ongoing leaks at a project called Brindley Place. The facade and associated coping flashings had been installed by a glazing sub-contractor that had ceased trading.
Our glazing refurbishment team attended site and conducted an initial site investigation to determine the cause of the leaks. The team identified a number of areas at the top of the facade and head coping flashings that had weak and in some cases missing sealing details.
Panels were consequently removed, EPDM membranes checked for integrity and in some cases replaced. Additional sealing work was then carried out to the interfaces between the coping flashings.
BAM were delighted with the work our team carried out and stated: Sam Lea, BAM Aftercare Manager: “Much appreciate the work Dortech completed last week I am yet to visit but told it was a first class job so thank you.”